| Illinois Department of Transportation (IDOT), is
preparing the environmental documents for review by the Federal
Highway Administration (FHWA). The FHWA is the Federal Agency responsible
for final approval of the environmental document. This study and
the supporting environmental documents will be governed by the National
Environmental Policy Act (NEPA) and state regulatory requirements.
Opportunities exist for the public to provide input into the alternatives
and project-related environmental impacts.
NEPA guides federally funded projects and projects that require
a Federal permit to lessen potential damges to the environment.
IDOT is required to evaluate alternative ways of accomplishing and
meeting study needs. They will assess the natural, built, and human
environment to determine the extent of impacts that may arise from
constructing and operating a project. Environmental factors such
as air quality, wildlife, vegetation, water quality, wetlands, geology,
neighborhoods, park/recreation areas, utilities, visual quality,
and cultural resources will be assessed. Public comments that are
received during the alternative analysis phase are considered in
the draft environmental document. Following NEPA guidelines, a document
called an Environmental Assessment will be prepared. The process
calls for continuous environmental evaluations as alternatives are
analyzed. If impacts are defined that may have significant consequences,
then an Environmental Impact Statement is prepared.
The development of the Environmental Assessment will be
directed throughout the following phases:
- Develop Purpose and Need
- Alternatives Analysis & Environmental Studies
- Draft Environmental Assessment
- Select Preferred Alternative & Mitigation Commitments
- Prepare Final Environmental Assessment
- Request to IDOT to initiate design phase
Project Phases
Alternatives Analysis
- Identify Goals and Objectives
- Develop Alternatives
- Evaluate Alternatives
Environmental Assessment Report
- Evaluate Alternatives
- Prepare Draft of Environmental Assessment
- Receive Formal Public Comment
- Select a Preferred Alternative
- Prepare Final EA/Approve Project